Prominence Plumbing will use a mini ex tractor to run all underground sewer and water lines before concrete is poured. We will run the sewer line to the tap. We will run our water yard line to the meter and tie in there. After rough in is complete we will test our lines to make sure there are no leaks before calling in for rough in inspection. After the slab is poured and the walls are framed we will return to run all drains, water, gas, and vents above ground. After completing top out we will test for no leaks and then call in for top out inspection. When the floors, cabinets and sheetrock is up we will return to install all fixtures provided by customer (Prominence will provide and install two tankless Water Heaters). After setting fixtures we will test one last time before cleaning up jobsite and calling in final inspection.